Wk51-2016 FLET loadout

pa-beach-amboin-img_6068-copy-copy

.i2017-season-greetings-4

screen-shot-2016-12-26-at-08-42-10At the yard  we finalize the stem welding on the FLET (Flowline End Termination). The structures were supplied for.
img_0710-kopie%cc%88ren

screen-shot-2016-12-26-at-08-44-49The stem-welding of the PIP (Pipe In Pip) is a high skilled job.img_0663-kopie%cc%88ren

screen-shot-2016-12-26-at-08-43-18From the welding area we transport the FLET by SPMT  (self-propelled modular transporter) 4* 6 liner with power pack to the quay.img_0664-kopie%cc%88ren

screen-shot-2016-12-26-at-08-42-00Here the FLET is lifted in DUO lift by the 300mt and the 750mt crawler cranes,dscn7885-copy

screen-shot-2016-12-26-at-08-41-32This load out operation is under control of the Yard Forman, dscn7891-copy

screen-shot-2016-12-26-at-08-43-51from the SPMT on to the barge.img_0675-kopie%cc%88ren

screen-shot-2016-12-26-at-08-42-10img_0673-kopie%cc%88ren

screen-shot-2016-12-26-at-08-41-48dscn7912-copy

screen-shot-2016-12-26-at-08-42-48dscn7907-copy

screen-shot-2016-12-26-at-08-45-51The safety officer keep a close look at the overall execution.dscn7892-copy

screen-shot-2016-12-26-at-08-43-18Project Manager Reinder Buren is responsible for the full organisation of the operation.dscn7897-copy

screen-shot-2016-12-26-at-08-41-48Touch down of the FLET with stem on the pre-installed barge supports.dscn7927-copy

screen-shot-2016-12-26-at-08-45-01img_0687-kopie%cc%88ren

screen-shot-2016-12-26-at-08-45-19The rigging is disconnected …dscn7930-copy

screen-shot-2016-12-26-at-08-42-55… and the cranes are moved back for the next operation.img_0709-kopie%cc%88ren

screen-shot-2016-12-26-at-08-42-48On the HAB (PTL) site, the first double joints are loaded out.img_0640-kopie%cc%88ren

screen-shot-2016-12-26-at-08-44-17Pipe clamps are installed img_0644-kopie%cc%88ren

screen-shot-2016-12-26-at-08-42-10and the pipes are lifted one-by-one into the pipe crates.img_0620-kopie%cc%88ren

screen-shot-2016-12-26-at-08-41-48The pre-fabrication of the spools is in its final stage. At the outside storage area the sub-spools are stacked in 3 layers.
img_0657-kopie%cc%88ren

screen-shot-2016-12-26-at-09-06-37

 

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google+ photo

You are commenting using your Google+ account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

w

Connecting to %s

This site uses Akismet to reduce spam. Learn how your comment data is processed.